Package # | VB-S-C-2019 CONSTRUCTION WORKS | QBE Nomination Closing Date | |||
Title | CONSTRUCTION WORKS | Tender Issue Date | November 12, 2018 | ||
Bid Closing Date | November 21, 2018 | ||||
|
Contract Scope
SAG and Ball Mill Lubrication Improvements
Install high-pressure pumps and delivery systems including filtering
Install Nitrogen Accumulators
Demolition of existing industrial equipment
Install associated electrical and instrumentation
Concentrator Glycol Heating System Upgrades
Install isolation valves and replace heaters on an existing glycol heat distribution system
Cyclone Pump Feed Box
Remove and replace existing corroded structural steel members
Concentrator Fresh Water Piping Replacement
Remove and replace approximately 300m of existing freshwater distribution piping with stainless steel
Larox Filter Press High Pressure Air Lines Replacement
Remove and replace high pressure air lines for three (3) Larox units
SAG Mill Feed Chute Replacement
Supply and Install new ore feed chute including liners
Concentrate Thickeners Repairs
Remove and Replace existing thickener tank walls and overflow launders
Apply new protective coating to thickener